Monday, July 16, 2012

Week 8 - Photo Wrap Up

Whew! With all of the dramatic demolition complete, work has steadily moved forward on the ground floor and with the stairwell skylight. The skylight has received its eight glass panels and should be complete by the week of July 16th. The stairwell, however, will remain closed throughout the ground floor renovation for construction crew access.

For the ground floor,we've heard a steady rhythm of hammering and drilling as new HVAC duct work has been installed, new electronic and data outlets wired, and backboard for tiles hung in the bathrooms. The upcoming week will feature insulation going into the walls, sheetrock/dry wall going up, and the bathroom walls getting tiled.

Perhaps best of all, the ground floor will now feature a water fountain (with a bottle filling station). You'll no longer have to head to the second floor to use our single water fountain. I think that's something we can all appreciate.

No comments:

Post a Comment